Making Room for the New–
Demolition of Old Pier Is Work for the Powerful V55

From our May 2002 newsletter


The "waterproofed" V55 breaks down pilings and seawall on the century-old pier.

New London, CT has one of the biggest and busiest ports in the world. Founded in 1646 as a whaling port it was home to as many as 80 whaling ships during its early years. Whalers no longer tie up in New London but freighters, ferries and fishing boats do.

Today the New London State Pier is made up of two 1100' piers serving barge, truck and rail transportation and two 50,000 sq. ft. warehouses. Large cargo ships pull into the two berths carrying mostly lumber, as well as steel and paper materials.

The turn-of-the-century piers had become dilapidated and were eventually condemned. The east pier was completely rebuilt several years ago and the west pier is currently being demolished and reconstructed. Blakeslee-Arpaia-Chapman, Inc. of Branford, CT was awarded the $10 million project of demolishing the old and constructing the new west pier. We spoke to Lou West, Equipment Supervisor, and Project Supervisor John Fucci about the 18-month project.

V55 Specifications:
Recommended Carrier Weight (US tons) 35-65
Working Weight (lbs.)
7,010
Flow Range (gpm) 63-84
Striking Rate (bpm) 440-1045
Adjusted Breaker
Pressure (psi)
2400
Tool Diameter (in.)
6.7
Overall Height w/Tool
& Bracket (in.)
126

Breaking Up Seawall
The old piers were made of timber and concrete with an earth-filled center. The concrete footings, timber pilings, and a 12'-14' high, 6' wide stone seawall running along both sides of the pier all had to be demolished. Gary Grana, Sales Rep. at W.I. Clark, Wallingford, CT, recommended a John Deere 370LC carrier equipped with a V55 breaker to break up the existing masonry seawall.

The rocks were broken into 300 lb. pieces. These are being used as rip rap to reinforce the new wall and help protect the new pilings from erosion. The pilings (18" in diameter and up to 40' long) are being driven right through the rock debris.

The demolition took approximately 3 months to complete and, according to West, the V55 made easy work of the task.

Underwater Challenge
Timing is almost everything on a job like this: Fucci explained that most of the rock breaking was done during low tide so the breaker wouldn’t be submerged too deeply in the water.

To make sure that water did not get into the oil and the hydraulics, the V55 was fitted with a Tramac Underwater Pressurization Kit. This is an easy-to-install accessory that attaches to a port on the upper part of the breaker with a unique and convenient swivel connection. A hose is threaded down the boom to an air compressor which continually flushes air through the circuit. The hose from the kit connection to the lower part of the boom is internal and protected.