 |
Vibro
Hammer Drives Pilings for Sewer Project
From our May 2002 newsletter
|
|
|
625SH
Vibro Hammer handling
pilings in busy downtown
New Haven
|
The
city of New Haven, CT is spending $4.5 million to replace its present
single-conduit underground water system with a new one that separates
sewer water from drainage. One of the benefits of the replacement
will be to save the city the expense of treating rain water.
Complete Construction Co. of Ansonia, CT, is placing approximately
20,000' of pipes under several blocks of some twenty streets. Depending
on usage, the pipes range in diameter from 24" to 36"
and are being placed 22' below the road surface.
Downtown New Haven has sandy soil which has to be shored up in order
to excavate. Complete Construction began by digging down about 6'
and laying 12' x 12' trench boxes. The trench boxes act as supporting
framework for metal sheet piling driven along two sides of the boxes.
Once the pilings are in place, work continues by excavating down
through the trench boxes. As each section is completed, the boxes
and sheet piling are removed and used on the next area.
At first, Complete Construction used a bucket to bang the piles
into the sandy soil. This was slow going and damaged the bucket.
Tim Germain of W.I. Clark Company, Wallingford, CT, provided the
solution by supplying a Tramac 625SH Vibro Hammer on a Hitachi 330.
The vibro hammer was perfect for the job. According to Tony Teixeira,
President of Complete Construction, the task of driving and extracting
piles became quicker and easier.
The 625SH Vibro Hammer is the largest of Tramacs four models.
The SH for Swivel Head refers to the tilt bracket which
allows the hammer to rotate 90° so its body is parallel to the
groundmaking it easy to clamp onto and lift sheet piling lying
flat on the ground. Tramacs vibro hammers are simple to install.
They are equipped with a valve that allows them to operate from
the excavators bucket circuit.
The New Haven job presents plenty of challenges, not the least of
which are the busy streets and difficult access. However, what Complete
Construction has been dealing with underground is even more of a
hassleutility wires and plenty of them. Since 20' sheets would
have torn through wires, the sheets are being driven down in sections,
deep enough to approach the wires but not interfere with them. Additional
pile sheet sections are placed below the wires, then the upper and
lower sections are pieced together.
Vibro
Hammer
Specifications: |
230SH
|
328SH
|
428SH
|
265SH
|
Recommended
Carrier Weight
(US tons) |
16.5-22
|
20-24
|
22-32
|
27.5-47.5
|
Total
Weight with Clamp (lbs.)
|
3015
|
3035
|
3210
|
3250
|
| Eccentric
Moment (in lbs.) |
191
|
278
|
348
|
522
|
| Driving
Force (tons) |
25-33
|
31-35
|
39-47
|
46-56
|
| Max.
Extraction Force (tons) |
11
|
11
|
14
|
14
|
Frequency
Range (rpm)
|
3000-3500
|
2800-3000
|
2800-3100
|
2500-2750
|
| Required
Oil Flow (gpm) |
23
|
29
|
45
|
53
|
|
|
 |