Vibro Hammer Drives Pilings for Sewer Project
From our May 2002 newsletter


625SH Vibro Hammer handling
pilings in busy downtown
New Haven

The city of New Haven, CT is spending $4.5 million to replace its present single-conduit underground water system with a new one that separates sewer water from drainage. One of the benefits of the replacement will be to save the city the expense of treating rain water.

Complete Construction Co. of Ansonia, CT, is placing approximately 20,000' of pipes under several blocks of some twenty streets. Depending on usage, the pipes range in diameter from 24" to 36" and are being placed 22' below the road surface.

Downtown New Haven has sandy soil which has to be shored up in order to excavate. Complete Construction began by digging down about 6' and laying 12' x 12' trench boxes. The trench boxes act as supporting framework for metal sheet piling driven along two sides of the boxes. Once the pilings are in place, work continues by excavating down through the trench boxes. As each section is completed, the boxes and sheet piling are removed and used on the next area.

At first, Complete Construction used a bucket to bang the piles into the sandy soil. This was slow going and damaged the bucket. Tim Germain of W.I. Clark Company, Wallingford, CT, provided the solution by supplying a Tramac 625SH Vibro Hammer on a Hitachi 330. The vibro hammer was perfect for the job. According to Tony Teixeira, President of Complete Construction, the task of driving and extracting piles became quicker and easier.

The 625SH Vibro Hammer is the largest of Tramac’s four models. The “SH” for Swivel Head refers to the tilt bracket which allows the hammer to rotate 90° so its body is parallel to the ground–making it easy to clamp onto and lift sheet piling lying flat on the ground. Tramac’s vibro hammers are simple to install. They are equipped with a valve that allows them to operate from the excavator’s bucket circuit.

The New Haven job presents plenty of challenges, not the least of which are the busy streets and difficult access. However, what Complete Construction has been dealing with underground is even more of a hassle–utility wires and plenty of them. Since 20' sheets would have torn through wires, the sheets are being driven down in sections, deep enough to approach the wires but not interfere with them. Additional pile sheet sections are placed below the wires, then the upper and lower sections are pieced together.

Vibro Hammer
Specifications:
230SH
328SH
428SH
265SH
Recommended Carrier Weight
(US tons)

16.5-22

20-24

22-32

27.5-47.5
Total Weight with Clamp (lbs.)
3015
3035
3210
3250
Eccentric Moment (in lbs.)
191
278
348
522
Driving Force (tons)
25-33
31-35
39-47
46-56
Max. Extraction Force (tons)
11
11
14
14
Frequency Range (rpm)
3000-3500
2800-3000
2800-3100
2500-2750
Required Oil Flow (gpm)
23
29
45
53