|
DA
450 Demolishes Sewage
Tanks Three Months
Ahead of Schedule!
From
our November 2004 newsletter
Lincoln,
NE. When Dan LaGrande of LeGrande Excavating reviewed the
specifications for the demolition of eleven sewage treatment
tanks for the city of Lincoln, NE, he anticipated it would take
ten days to demolish each one. The structures were 105' in diameter,
16' tall and 18" thick -- a big undertaking! The $2 million
demolition contract is part of a $50 million expansion of the
sewarge facility including a new plant.
Working with his salesman, Jeff Smith of James W. Bell, Omaha,
NE, LaGrande purchased a DA 450 with an MC concrete cracking jaw
and mounted it on a CAT 330C.
LaGrande told us the DA 450 "ate the concrete like it was
going out of style." It performed far better than he
anticipated: each tank took only three days to demolish! The concrete
and rebar were crushed and cut to the size needed for recycling
(6" in diameter) in a single jaw closing, and carted off.
The project was completed three months ahead of schedule.
According to LeGrande, they were dealing with #11 rebar as well
as #6 and #8, easy work for the powerful MC concrete cracker jaws.
LeGrande filled the holes left after the tank debris was removed
with 100,000 yards of dirt.
The DA 450 Keeps Busy
LeGrande has since used the DA 450 on numerous sites and has chosen
to keep it on the carrier as a dedicated machine. He estimated
the unit has already put in 500 to 600 hrs. and he can't
say enough good things about its performance. He told us that
on the last job, it "ate #11 rebar like a toothpick".
He says the 360-degree hydraulic rotation is a big plus, making
it much easier for the operator to maneuver, and the crushing force
is very impressive. He also commented that despite the size and
weight of the DA, it was very stable, even with the "long stick"
of the 330C.
|